Wednesday, 11 July 2012

Day 6 of bathroom works

Today the cloakroom floor went down, and the sink went in.
The bath is in place upstairs.
Most of the lights are in place.
Shaver socket done.
A bit nervous now... Are we running out of time for the bathroom finished for Friday?






Tuesday, 10 July 2012

Day 5 of bathroom fit

Today we got plastered.
Ready for unit fit tomorrow.
British Gas called. They are coming to check the power flush next Tuesday.




Monday, 9 July 2012

Day 4 of bathroom fit

Old towel rail defunct.
Prepared for plastering.





Saturday, 7 July 2012

Day 3

Bees or wasps in the attic. Pipe work tidied up.


Thursday, 5 July 2012

Day 2 air locks and sludge

Plumbing work... Air locks and sludge in the radiators when they were disconnected. Looks like British Gas didn't power flush the system last year as they said they had, so we have to complain now.



Bathroom day 1

Out with the old...




Tuesday, 3 July 2012

Bathroom improvement day -1

We are getting ready for the builder to arrive tomorrow to do the bathroom, cloakroom and chimney. There is a lot to do.