Thursday, 19 July 2012

Bathroom day 11

Today we had the heating system powerflushed by British Gas and the guys checked over the shower. It's failure to work yesterday was blamed on an "air lock"
Time to wait and see I think.
The British Gas guy left us a glass of clean water from our clean system. Nice touch!

Bathroom day 10

All done, except paint and trim. But shower is not working. Plumber coming back.
Extractor fan installed.
Black grout has marked the walls but that will paint over.





Tuesday, 17 July 2012

Bathroom day 9

Today the toilet and sink install was done. Tiling and shower screen to do.




Sunday, 15 July 2012

Bathroom day 8

Cloakroom pretty much done.
Bath working. Toilet, sink, and shower to go.




Thursday, 12 July 2012

Bathroom day 7

Today saw the tiling, towel warmer, and basics in the bathroom. The cloakroom is nearly done.






Wednesday, 11 July 2012

Day 6 of bathroom works

Today the cloakroom floor went down, and the sink went in.
The bath is in place upstairs.
Most of the lights are in place.
Shaver socket done.
A bit nervous now... Are we running out of time for the bathroom finished for Friday?






Tuesday, 10 July 2012

Day 5 of bathroom fit

Today we got plastered.
Ready for unit fit tomorrow.
British Gas called. They are coming to check the power flush next Tuesday.